Blower door test calculations.
The formula is cfm50 x 60 the volume of the house.
Typical p n building values are 5 10 20 30 40 and 50 pascal.
Simply put a blower door is a diagnostic tool used to measure how much air infiltration air leakage occurs in a house.
So if your blower door cfm50 reading is 1000 cfm and house is 30 x 40 x 8 tall the ach 1000 x 60 30 x 40 x 8 6 25 ach.
After installation of the complete air distribution system but before installation of insulation and sheet rock.
Cubic feet per minute of air leakage at 50 pascals of pressure.
If its blower door flow at 50 pa is 2200 cfm then the air changes per hour ach50 are.
A blower door test is used on buildings in order to quantify the amount of air leakage through its enclosure.
Ordinary least squares regression analysis is then used to calculate the leakage characteristics of the building envelope.
The air change rate must be below 0 6 airchanges per hour under test conditions.
Understanding blower door test results.
The low air leakage rates that are required in the standard must be proven for each individual building by means of a blower door air tightness test.
The building or dwelling unit shall be tested and verified as having an air leakage rate of not exceeding 5 air changes per hour.
1291 m 3 h.
The multi point blower door test procedure results in a series of known values of q n fan and p n building.
It is equal to the blower door flow for one hour divided by the house volume in cubic feet.
During this test a calibrated fan is installed in an otherwise sealed door or window while all the other openings to the exterior are closed.
When the fan is turned on it creates a pressure difference between the outside and the inside.
Total air flow through building envelope.
Where required by the code official testing shall be conducted by an approved third party.
Hole size m 2 4pa.
Last year we built an energy star home for a customer and we used a blower door test to evaluate the houses air infiltration performance.
Duct testing calculator new construction air leakage testing calculator blower door test cfm50.
Ach50 cfm50 60 house volume for example if a house is 40 ft by 50 ft by 8 ft high then its volume is 40 50 8 16 000 cubic ft.